Conducted Immunity Testing
Conducted RF immunity, electrical fast transients, surge and voltage dips, tested on your product's power and signal cables in our ISO/IEC 17025 accredited lab or at your site.
- Four Disturbances, One Program: IEC 61000-4-6, 61000-4-4, 61000-4-5 and 61000-4-11 planned together, the way product standards call for them.
- Lab or On-Site Testing: Conducted RF, EFT and surge can be run in the field for machinery, switchgear and installed systems, and dips can be tested on site too.
- North American Surge Practice: IEEE C62.41 and C62.45 for AC power circuits and IEEE C37.90.1 for protective relays, alongside the IEC methods.
- Engineers Who Debug With You: When a port fails, our engineers help find the path and retest once your fix is in.
Accredited EMC testing

ISO/IEC 17025
A2LA #5179.02

FCC recognized
Part 15/18/22 · wireless

ISED recognized
CAB CA0102
* Tell us your requirements for a detailed quote and project timeline. We’ll respond within 24 hours.
What is conducted immunity testing?
Conducted immunity testing checks whether a product keeps working when electrical disturbances arrive on its power, signal and control cables. In the strict sense it means IEC 61000-4-6, which injects radio frequency energy onto cables; in practice a conducted immunity program also covers electrical fast transients (IEC 61000-4-4), surge (IEC 61000-4-5) and voltage dips and interruptions (IEC 61000-4-11), which the generic and product EMC standards behind CE marking typically call for together.
It is the mirror image of conducted emissions. Fields that reach the product through the air are covered by radiated immunity.
Why do products fail conducted immunity tests?
Every cable is an antenna and a path in. A nearby radio transmitter induces RF current on a long sensor lead. A contactor switching a motor sends bursts of fast spikes down the supply. Nearby lightning puts a surge on the mains.
The result is drifting readings, dropped links, resets and, on surge, protection parts that fail open or short. Most trace back to filtering, grounding or transient protection at the port, which is why we test port by port.
Conducted RF immunity to IEC 61000-4-6
IEC 61000-4-6 simulates RF from transmitters such as two-way radios and broadcast stations, as picked up by the cables attached to your product. The standard applies a disturbance swept from 150 kHz upward, amplitude modulated, to each power and signal port in turn. The product standard picks the level, the frequency range and the ports.
| Level | Test voltage (e.m.f.) |
|---|---|
| 1 | 1 V |
| 2 | 3 V |
| 3 | 10 V |
| X | Special |
Levels from IEC 61000-4-6:2013 (Edition 4.0), Table 1: r.m.s. value of the unmodulated signal, which is then 80 % amplitude modulated at 1 kHz.
Coupling methods
Coupling depends on the port:
- Coupling/decoupling networks (CDNs) for power lines, telecom lines and screened cables.
- Bulk current injection with a current probe where a CDN cannot be inserted, such as multi-conductor data cables.
For automotive components, the bulk current injection counterpart is ISO 11452-4, which we also test to.
Electrical fast transient and burst to IEC 61000-4-4
EFT testing reproduces the bursts of fast, repetitive spikes created when inductive loads such as relays, contactors and motors are switched. Bursts are applied to AC and DC power ports through a coupling network, and to signal and control lines through a capacitive coupling clamp, in both polarities. Protective relays are tested to IEC 60255-26.
| Level | Power ports and earth | Signal and control ports |
|---|---|---|
| 1 | 0.5 kV | 0.25 kV |
| 2 | 1 kV | 0.5 kV |
| 3 | 2 kV | 1 kV |
| 4 | 4 kV | 2 kV |
| X | Special | Special |
Levels from IEC 61000-4-4:2012 (Edition 3.0), Table 1: open-circuit peak voltages, at a repetition frequency of 5 kHz or 100 kHz.
Surge immunity to IEC 61000-4-5 and IEEE C62.41
A surge is a single high-energy transient caused by lightning or large switching events on the power network. IEC 61000-4-5 applies a combination wave line to line and line to earth on power ports, and to outdoor or long-run signal lines, at set phase angles and in both polarities.
| Level | Line to line | Line to earth |
|---|---|---|
| 1 | Not applicable | 0.5 kV |
| 2 | 0.5 kV | 1 kV |
| 3 | 1 kV | 2 kV |
| 4 | 2 kV | 4 kV |
| X | Special | Special |
Levels from IEC 61000-4-5:2014+AMD1:2017 (Edition 3.1), Table 1: open-circuit test voltages, applied at every level up to and including the target.
For equipment sold into North American markets, we also test to IEEE C62.41 and C62.45, and to IEEE C37.90.1 surge withstand capability for protective relays and substation equipment.
Voltage dips, interruptions and variations to IEC 61000-4-11
IEC 61000-4-11 checks how an AC-powered product rated up to 16 A per phase behaves when the mains sags, drops out briefly or varies over a longer period. A dip can reboot a controller, wipe settings or stall a motor.
| Class | Voltage dips | Short interruptions |
|---|---|---|
| 2 | 0 % for 0.5 cycle; 0 % for 1 cycle; 70 % for 25/30 cycles | 0 % for 250/300 cycles |
| 3 | 0 % for 0.5 cycle; 0 % for 1 cycle; 40 % for 10/12 cycles; 70 % for 25/30 cycles; 80 % for 250/300 cycles | 0 % for 250/300 cycles |
Levels from IEC 61000-4-11:2020 (Edition 3.0), Tables 1 and 2. Percentages are the voltage that remains during the event, and cycle counts are given for 50 Hz / 60 Hz.
DC-powered equipment is tested to IEC 61000-4-29 for dips and interruptions on the DC input, and IEC 61000-4-17 covers ripple on DC supplies.
Industrial and utility standards may also call for common mode disturbances (IEC 61000-4-16), ring wave (IEC 61000-4-12) and damped oscillatory wave (IEC 61000-4-18), which we test to as well.
Performance criteria
The product standard names an acceptance criterion for each test. Criterion A means normal performance throughout. Criterion B allows performance to degrade during the disturbance, with no change of operating state or stored data. Criterion C allows a temporary loss of function that recovers by itself or through the controls.
Which standards call for conducted immunity testing?
Some of the standards we test to that call for these methods include:
| Standard | What it covers | Typical products |
|---|---|---|
| IEC 61000-6-1 / IEC 61000-6-2 | Generic immunity, residential and industrial | Products with no specific EMC product standard |
| IEC 61326-1 | Measurement, control and laboratory equipment | Instruments, analyzers, process sensors |
| IEC 60601-1-2 | Medical electrical equipment | Patient monitors, therapy and home-use devices |
| CISPR 35 / EN 55035 | Multimedia equipment immunity | IT, AV and networking equipment |
| EN 50130-4 | Alarm and security systems | Intrusion, fire and access control panels |
| EN 50121 series | Railway applications | Rolling stock and trackside equipment |
| IEC 60255-26 / IEEE C37.90.1 | Protective relays | Substation protection and control |
| IEEE 1613 / IEC 61850-3 | Substation communication devices | Utility switches, routers and gateways |
| EN 61131-2 | Programmable controllers | PLCs and I/O modules |
| IEC 61800-3 | Adjustable speed drives | Variable frequency drives |
| EN 62040-2 | Uninterruptible power systems | UPS units |
| ISO 11452-4 | Automotive bulk current injection | Vehicle electronic modules |
Korean KN and KS C 9610-4 equivalents are also available for KC. Our accreditation and certificate are on our accreditations page.
Can conducted immunity testing be done on site?
Yes. Conducted RF immunity, EFT, surge and voltage dips are all tests we perform in the field, using the same standards as in the lab. Conducted RF, EFT and surge suit production machinery, switchgear and systems already installed at a plant. ESD and power frequency magnetic field testing can be added to the same visit.
How a conducted immunity program runs
- Test plan. We list every port, the tests and levels it gets, and the performance criteria.
- Setup. The product is laid out on the ground reference plane with the specified cable lengths and a coupling network or clamp on each port.
- Testing port by port. The RF sweep, bursts and surges in both polarities, then dips and interruptions on the supply.
- Monitoring. We watch the product through the agreed method, such as your test software or a communication link, and log any anomaly against its port, test and level.
- Report. You receive an accredited test report with the ports tested, levels, observations and the criterion met.
EFT and conducted RF checks can also be added to an EMC pre-scan visit.
Technical specifications
- Conducted RF: 150 kHz to 230 MHz; CDNs for power, telecom and screened cables; bulk current injection
- EFT: power port coupling network and capacitive coupling clamp
- Surge: line to line and line to earth on power ports
- Dips: AC and DC supplies
- Location: our lab in Aurora, Ontario, or at your site
Why test conducted immunity with Megalab?
On-site testing for all four tests. Installed and oversized equipment can be tested where it stands.
Utility and relay standards. IEEE C62.41, C62.45, C37.90.1 and IEC 60255-26 sit alongside the generic and product standards.
Engineers in the room. Our team works through port failures with you as they happen.
One lab for EMC, safety and environmental. An industrial controller can go through surge, electrical safety and vibration testing in the same building.
What we need to quote your conducted immunity test
- Product type, photos, dimensions and weight
- Power: AC mains (single or three phase) or DC, with supply voltage and current
- Every port, with its cable length
- Target markets, the product standard and the levels, if known
- Operating modes, and how we can tell the product is working correctly
- Samples available, lab or on site, and whether you want a pre-scan first
Send us the details and we will confirm the requirement and quote it. We respond within 24 hours.
Conducted immunity FAQ
IEC 61000-4-6 is the conducted RF immunity method. EFT, surge and dips use IEC 61000-4-4, 61000-4-5 and 61000-4-11. Your product or generic standard, such as IEC 61000-6-2 or IEC 60601-1-2, says which apply and at what level.
Conducted immunity injects disturbances onto the cables, at the lower frequencies where cables are the main pickup path. Radiated immunity exposes the whole product to an RF field from an antenna, at higher frequencies. Most product standards require both.
EFT applies bursts of many very fast, low-energy spikes, like those from switching a relay or motor. Surge applies a small number of slower, high-energy pulses, like those from lightning or grid switching.
AC and DC power ports, signal and control ports, and telecom ports, with the product standard deciding which apply. Ports with short cables are often exempt from some tests.
We record the port, test and level, and our engineer helps you find the cause. Once you have a fix, we retest the affected ports.
Ready to test? Send us your product details and we will confirm the requirement and quote it.
Related tests: ESD · Radiated immunity · Conducted emissions · Flicker and harmonics · EMC pre-scan
Your Partner for EMC Compliance
Four Tests, Planned Together
Conducted RF, EFT, surge and dips on each port your standard lists.
Testing Where Your Equipment Stands
On-site conducted immunity for installed systems.
Accredited EMC Testing
ISO/IEC 17025 accredited by A2LA, certificate 5179.02. See our accreditations.